Sunday, February 28, 2010

Substation fire protection system

All electrical substations and main switchrooms need to be provided with a fire protection system. This post try to provide beginners with some  pictures to help them grasp a minimum degree of basic understanding on fire protection systems for electrical substations.

Picture a1 - Electrical substation CO2 cylinder tanks
(Click on the picture to enlarge it)

=================
RELATED ARTICLES:
Substation rooms layout diagram | Building’s electrical room layouts | Electrical busduct installation pictures |  Electrical installation pictures

=================

If an electrical substation building is designed and constructed as a separate building, the provision of portable fire extinguishers as the sole form of fire protection may be accepted by authorities as adequate.

It is quite common for some local offices of the electricity supply authority and local offices of the Fire Department to follow this practise.

However, major substation rooms that are part of an occupied building are usually required to have some form of an automatic fire extinguishing system such as a CO2 system, or a clean agent fire extinguishing system.

Picture 1 – CO2 fire protection cylinders being installed


The above picture shows a CO2 automatic fire extinguishing system being installed inside a standby generator room under construction.

When I wrote this post, the building was still under construction. So the standby generator room was not yet fully completed.

What system to use
What fire protection system to be used for a substation depends on the preference of the design consultants, and the minimum requirements of the local Fire Authorities.

If the substation room involved is also to be handed over to the electric supply authority, then the minimum requirements and preferences of the local office of the electric supply authority should also be taken into account.

The fire authorities usually have an already established requirement of what system is required in a substation room.

The engineering consultant's design engineers usually prepare their initial designs based on these requirements.

These initial designs are then coordinated with the main building design which usually is the territory of the design architect for the building project.

Here I am talking about electrical substations and other electrical rooms of a building project.

Electrical substation buildings that belong to the electricity supply authorities' distribution network is a different matter altogether with regard to fire protection systems. This post does not cover those substations.

After completion of the initial design, the project's design architect then submits a number of sets of relevant architectural design drawings to a number of authorities and local municipalities for review and approval.

The local Fire Authority is also part of the list that requires drawings submission from the building design architect.

These are the drawings of "passive fire protection". Detail explanation of passive fire protection may drag me off the topic of substation fire protection too far.

So I will do that in some other separate post.

Lets just say for now that a passive fire protection is a design of the buildings' overall layout and their building components with respect to danger to human lives and properties in the event of a fire.

This involves among other things how the building layout is designed to allow occupants of the building to escape quickly and safely during fire;
how a fire that started in one part of the building is prevented from spreading to other part of the building;
how is the layout designed to allow and help the fire fighters fight fires;
how many hours the related building components (i.e. fire doors) can prevail during fire; and so on.

Related to this also is the emergency lighting system that is needed by the occupants in the event of a fire so that they can see the escape paths; also the "EXIT" signs that are supposed to guide them to exit the building or to designated "fire-free" areas.

These are among the details on the drawings submitted by the architect to the local Fire Authority.

These details are called static fire protection.

The "active" fire protection systems are not submitted yet to the Fire Authority.

As I just said, the building layouts are designed by the Architect with the help of engineers which include civil and structural engineers, and also the mechanical and electrical engineers.

The "active" part of the fire protection system is the part that actually monitors, detects, and extinguishes fires.

Also the parts that involve pumps and piping that would be used by the firemen (or anyone for that matter) to fight fire.

Included here also are the communication system that can be used during a fire situation, which include a public address and announcement system, and firemen intercom system.

This is the part that is designed by mechanical and electrical engineers.

It therefore follows that the submission of the active fire protection to the Fire Department should be done by the mechanical and electrical engineers.

So after the submission of the passive fire protection system has been approved by the fire authority, the submission of the active fire protection commences.

This submission is done by the mechanical and electrical design engineers (also called "MEP engineers" in some part of the world).

The process of reviewing and commenting on the drawings submission by the fire authority may take one to three months to complete.

However, once the passive fire protection drawings have been approved, then the actual construction works of the buildings (including the substation buildings if it is separate from the main buildings) can commence.

What is an active fire protection system?

The CO2 system in Picture 1 above is one example.

This system monitors all rooms in the substation for signs of fire. It triggers an alarm if signs of a fire are detected, either in the form of heat or smoke.

If the signs of smoke meet a certain design criteria, the "fire fighting system" is triggered to extinguish the fire.

This is an over-simplified description of a fire fighting system.

However it should be enough to give beginners an initial understanding of how a fire fighting system in substations and electrical rooms work.

Below are a few more pictures of the fire protection system for the electrical substation rooms in the same project as Picture 1 above.

I also give very brief descriptions of how it works here.

At the end of this post, I attach more pictures on fire protection with a brief description for each picture.

Likewise, over time I will keep adding more pictures at the bottom of this post. In this way I can give you pieces of information on this topic without the burden of having to write a new article for each new photo.

This may also help to minimize the number of post titles that I need to write on fire protection systems.

I do not wish to confuse Google's search engine into thinking that this blog is also a blog on fire protection system, which is a topic  under mechanical, not electrical.

Picture 2 – Weatherproof CO2 panel


(Click on the picture to enlarge it)

Picture 2 above shows the CO2 control panel outside a transformer room at the same building as Picture 1.

A CO2 control panel usually acts as an independent local fire control panel.

In a large building or complex, the local fire panel is connected to a Main Fire Control Panel of the building complex.

The main fire control panel is usually located in the building's Main Control Room and is usually manned by employees assigned by the building management.

Some of the alarm signals and indications on the local fire panel (the CO2 control panel in this case) are repeated at the main fire control panel.

Observe the components of the automatic fire fighting system that are visible in Picture 2.

The alarm bell is self-explanatory.

It is selected to produce an audible alarm ringing of at least 5 dBA above the ambient noise or a minimum of 65 dBA, whichever is greater.

This is a common design criteria.

The ringing sound should be the trembling type, not the single stroke sound, and it should be sustained for a minimum period of 30 seconds.

The bell must operate from the fire alarm battery and any fault on the bell circuit should not have any effect on the transmission of the fire signal to the main fire control room or to the Fire Department's monitoring station.

Automatic detection of fires

The automatic detection of a fire inside a substation room or an electrical switchroom can be done by either by a smoke detector or heat detector.

The usual practice is usually by a combination of both.

The system inside Picture 2 above used two smoke detectors and two heat detectors.

This is a common practice for individual electrical room spaces such as transformer rooms or small switchgear rooms.

If a room is large, more detectors may be required depending on the the room's actual size.

Picture 3 – FM 200 fire extinguishing system



The CO2 system has been a widely used type of fire extinguishing system since I can remember. However it is now being slowly phased out. The reason being the gas is highly lethal.

There have been a considerable number of fatality cases due to the system discharged by accident while workers were still working inside the substation room.

Picture 3 above is one of the alternatives to the CO2 system. This one is called FM 200 and this picture was taken while the installation is progress for a server room in an office building.

Picture 4 - Portable fire extinguisher inside a 33kV substation
(Click to enlarge the picture)

Observer the elaborate markings of the location of the portable extinguisher: the painted marking on the wall and floor, the signage and the extinguisher numbering on the wall.

This is a clear statement of how important the portable extinguishers are in a 33kV substation, and how important it is to have them provided with markings that stand out.

During the starting moments of a fire incident, every second counts. It is therefore extremely important for the personnel inside the substation to be able to locate the extinguishers quickly.

Picture 4a - A close up view of the portable extinguisher

Picture 4b - A portable extinguisher outside the construction site office of a building project



Picture 5 – Mounting hook for a portable fire extinguisher


This is the end of this post.

Below you can find more pictures of fire protection systems for electrical substations.

In future I will keep adding more of similar pictures at the bottom,  not just for electrical substations but for other areas of buildings also.

xxx ADDITIONAL PICTURES XXX

Picture 06 - Main control panel and firemen intercom master panel at Fire Control Room

(Click on the picture to enlarge it)

The above picture shows part of the equipment installation in progress in Fire Control Room of a building complex.

As I briefly explained at the beginning of this post, when the substation is part of a building complex, all fire fighting control and monitoring systems at each

mechanical and electrical plant rooms, including at electrical substation rooms, are connected to a central fire control panel of the building complex.

What you can see in Picture 06 are the Main Fire control Panel and the Fireman Intercom Master Panel.

I labelled also where the master panel's mimic diagram is. Of course you cannot see the mimic diagram there.

The glass window of the mimic panel was covered with a thick cardboard to give it some degree of protection during the installation.

This picture was taken during the last phase of the building construction. As usually is the case, this was the period when all equipment inside the Fire Control Room

would be delivered to the room, fixed to their designated location, wiring works connected the equipment, tested and and commissioned.

Many parties are involved here during this period.

Besides the master panels that you see in the picture, there are others also in the same room: Lift control and monitoring panel, Building Control System master panel,

Public Announcement and Firemen Emergency Announcement Master Panel, and Closed Circuit Security Camera (CCTV) Master Panel.

All of these in the same room.

Why? Because this is generally where the 24 hour central security station would be located.

I said generally because the precise arrangement varies depending on the management team responsible for the building.

First point of contact for firemen during fire

In the event of an actual fire, this is where the firemen team would come first when they arrive at the scene afer report of a fire.

Even when the fire is at a substation which is in a separate building beside the main building complex.

Arrangement of location of the Main Fire Control Room is an interesting topic of its own. Maybe I will consider a sending a separate post just for it.

The Firemen Intercom Master Panel

In a large building complex, fighting fire is an extremely high risk job.

Firemen need to enter the building under the thick of fires, smokes and falling objects.

The firemen need a reliable communication facilities to talk to the fire chief commanding the fire fighting and rescue operation.

The firemen intercom is for that purpose.

At each landing of a fire escape staircase, one unit of the intercom console is provided and it is wired via a fire resistant telecommunication cable to a master

panel similar to one in Picture 06 above.

Even the fire intercom consoles inside our electrical substation are also connected and monitored from this master panel inside the Fire Control Room.

The more consoles that are installed in a building complex, the bigger the dimensions of the master panel would be.

Picture 07 - Firemen Intercom Master Panel

(Click on the picture to enlarge it)

This is a photo from another picture shot.

As you may have guessed, the firemen who is stationed here during a fire fighting and rescue operation would have a "helicopter view" of the whole building area.

Picture 08 - Closer view of the Firemen Intercom Master Panel


I zoomed in into the "mimic" of the master panel and added a few labels to give beginners a deeper understanding of Firemen Intercom Master Panel.

Observe the labels "CALL indicator" and "FAULT indicator".

Below the CALL on the mimic is a column of red-coloured lights (small very low-powered LED lamps). One for each location. I have labelled a few of the location to help

you understand better.

Beside each red LED is another similar LED of somewhat dark yellow color.

Now, if during a fire, a firemen who climbed up the fire escape staircase No 3 reaches the landing of the staircase at 19th Floor. If he picks up the firemen intercom

at that staircase, then the red LED on the console would light up.

This way he can communicate with his operation chief in the Main Fire Control Room. You can see an example of a fire intercom console  in Picture xx below.

During real fire fighting, fire fighters often cannot see anything beyond a few feet. He may not know precisely where he is. So if he picks up a firemen intercome,

then the chief in the control room can tell him precisely where he is.

Now the dark orange light next to the red one.

If the telecommunication cable is broken for some reason, for example due to some recent renovation work, then the dark yellow LED would light up.

Since the Fire Control Room is always attended by security personnel, someone would immediately know that this particular console is faulty and cannot be used.

Immediate action can then be taken to bring it back into normal service.

All systems and equipment for fire detection and fire fighting are there to protect human lives and properties.

Because of that, especially on he human lives part, their integrity and proper functioning at all times should never be compromised.

Picture 09 - The amplifier rack of a PA and Emergency Announcement System


I took this picture behind the amplifier rack of the PA and Emergency Announcement System in the Fire Control Room of a building project.

I apologize for the poor quality of the picture but this is the only one that I got.

I do not exactly go around taking pictures for this blog. I do what I do, and when I want to send a post for this blog I just search from whatever pictures in my hards

drive.

Sometimes I get lucky and the readers get to see nice pictures. At other times, my shots are just so bad it makes me wonder why I didn't check the quality of the

pictures immediately after I took them.

Picture 10 - The cabling behind the PA amplifier rack


This one is a bit better. It is from the same panel. I took the shot just to keep a record of the quality of the work in progress in case I need them later.

Picture 11 - Horn speaker at a basement carpark
(Click on the photo to enlarge it)

A high quality sound amplifier costing hundreds of thousand of dollars is of no use without the speaker to bring the sound to the public.

The above picture shows a horn speaker at a basement carpark. It is actually in the same project as the amplifier picture above.

Picture 12 - A close up view showing the wiring conduit also

Picture 13 - A close up view showing the mounting bracket and the wiring cable into from the conduit into the speaker unit

Picture 14 - Wall mounted box speaker above a staircase landing

Picture 15 - Security CCTV Master Panel in Fire Control Room

This one control panel has nothing to do with fire protection at all.

However, in real life design and construction of a building complex, it is an equipment that need to be closely coordinated with fire control and fire fighting

equipment inside the building control room.

Just look at the sheer size of the CCTV master panel. If not properly planned for during the design of the building layout, it can cause a real conngestion in the fire

control room.

Beginners should take note here. Even though architect can choose where she wants the fire control room to be, eventually the location is dictated by Fire Authority.

Once the design drawings are submitted to the Fire Department for approval, the fire officers can start exerting their power.

The best place for a fire control room is around the main entrance of the building, at the ground level.

During fire emergency, it is not good to have the fire fighters running around looking for fire control room. Every second lost can mean one more life lost in a real

bad fire situation.

Main entrance at ground floor is the best place for the main control room.

Guess what?? That is also an are with the highest price tags in a commercial building.

No building owner in their right mind would surrender such valuable commodity in big quantity.

In fact, after the design drawings have been approved by the fire authority, an owner may even squeeze down the size of the fire control room, citing all sorts of

commercial reasons.

That is why the control room should be properly sized for during design.

During construction, the supervising engineers should be vigilant to ensure that all equipment are manufactured to dimensions not exceeding the planned dimension.

Failure to exercise care here can affect someone's job security in that project.

Picture 16 - Another view of the CCTV master panel

I show this picture because I know there is always someone out there that need some ideas how to plan for this panel, especially young engineers in a design office.

So now you have some ideas of what to do, right?

Picture 17 - Example of a separate building for electrical substation

(Click on the picture to enlarge it)

I have explained at the beginning of this post about how good it is to design an electrical substation as a separate building near the main buidling complex.

Actually that applies to all mechanical and electrical plants that serve the building.

The above picture show one example that I can I can immediately show you.

I will not elaborate on this picture today. Readers can just study the picture and try to identify the plants.

I will send a short post just to explain on this picture some time in the near future.

Copyright http://electricalinstallationwiringpicture.blogspot.com Substation fire protection system

Tuesday, February 23, 2010

Electrical installation pictures

If you are looking for pictures of temporary electrical installations, they can be found at another post, Temporary electrical installation pictures and Temporary lighting installation pictures.What you will find below are mostly on permanent installations.

Picture 1 – Conduit and trunking



The above picture shows how the electrical conduit and trunking installation should be coordinated with water pipes.

Trade subcontractors (water piping sub-contractors, electrical sub-contractors, telephone cabling contractor, computer network contractor, etc) must not be allowed to proceed with the installation of their individual services and equipment on the “first come, first served basis”.

=== RELATED POSTS: Pictures of electrical wiring |

===================

Prior to the commencement of the installation works by trade sub-contractors, a set of proper coordinated drawings, endorsed by all relevant parties, should be made available to all the sub-contractors involved in a particular area.

Feedbacks from them should be heard because they are the ones who will be doing the works. Many times, what are nicely shown on approved drawings cannot be practically constructed at site.

You will find more pictures on this matter in Electrical conduit and trunking pictures.

Picture 2 – Electrical grounding electrode and chamber



An electric shock protection system depends on heavily on the availability of good and reliable connection to the earth mass.

Without the low resistance to earth, the users of electricity face a very high risk of electrical injuries and electrocution.

Therefore, the connection to the grounding electrodes must be properly installed, protected from accidental damage and easily available for inspection and maintenance.

The component used to house the earthing connection to the grounding rod is called earthing chamber.

Picture 2 above shows an example of such a chamber. It is usually made of concrete materials and provided with removable cover.

Inside the chamber, what you see is the earthing copper tape that has been connected to the earthing electrode. However, in this picture the connection is not so visible.

Picture 3 below gives you a better view of a connection to the earthing rod. This earthing point was still under construction when the picture was taken. So the earthing chamber was not put into place yet.

Because of that, you can have a good view of the connection between the earthing conductor and the grounding electrode.

Picture 3 – Connection between an earthing conductor and the grounding rod



See more of the earthing chambers and the electrode connections in this post, Electrical grounding electrode pictures.

Picture 4 - Down light pictures



Down light are one of the most popular types of lighting fixtures inside buildings.

It is not a new type of light fittings. but with the popularity of compact fluorescent lamps, the surge in the use of downlights has increase dramatically.

I will be talking about these types of light fittings soon, but i have already sent a few pictures of down lights and other types of fluorescent light fixtures at this post, Recessed down lights installation.

Diagram 5 – Sectional diagram of a simple lightning protection system



I have sent a post on Lightning earth rods installation. It is the first of a few posts on the subject of lightning protection system for buildings.

There are a few pictures there, but I have not yet uploaded really good pictures on lightning protection.

However, the content of the article is suitable for beginners who wish to get some overall knowledge on the issues of lightning strikes and lightning protection.

Check it out.

Picture 6 - Installation of lightning air termination network



This is part of a lightning air termination network. The installation work at the roof of this building is actually in progress now and is not yet completed.

However, I have taken a few pictures of what has already been installed. You can see the rest of the pictures at this post, Lightning roof conductor installation.

Picture 7 - Leaking hose reel pipe



Why do I show you a picture of leaking hose reel water pipe?

Because water and electricity do not mix, yet there are many water piping of all types running around inside a building near our electrical cables, equipment and appliances.

Many of serious electrical accidents and injuries have been a direct result od water that come into contact with electricity.

Even when no accident occurs, electrical equipment would get damaged when it is involved with water unless is has been designed to be so.

Visit this post, Electrical panel under water pipes, to read a few pictures of one case that I recently documented.

Picture 8 – Typical busduct rising main at individual building floors



The above picture shows a typical installation of busduct rising mains in the riser room at individual floor of a high rise building.

This picture was taken in the riser room at one of the upper floors of a high rise building.

From the picture you can see most of the major components of a busduct riser system.

(NOTE: for readers who are not from electrical disciplines, a “riser” is a feeding cable or pipe giving supply to upper floors of a multi-storey building.

In electrical works, a riser is a set of cables the supply the upper floors. The electrical distribution diagram in Diagram 3 may make you understand this better.

The feeding cables “rise” up straight to the top floor. Then at each floor a tap-off unit is connected so electricity can be supplied to that floor.

An alternative is to run one individual set of cables to each floor. Then there would be many cables that need to be installed the number of which is directly proportional to the number of upper floors.

One single set of bigger cables is always cheaper to install and much easier to handle.)

Observe that there are three tap off units there: two units of 60A three phase, and one unit of 100A three phase. The one at the highest position of the three is the 100A tap off.

Why three units?

Visit this post, Electrical busduct installation pictures, to read more and see more pictures and diagrams of busduct risers in multi-storey buildings.

Picture 9 - Surface conduit installation



Why do we need these conduits?

The conduits are used to protect the wiring cables that carry the electrical current.

Electricity is dangerous. Even though the electric conductors that carry the current is insulated by some PVC covering materials or whatever, the covering material is not strong enough to protect the cable from damage.

When the covering is damaged, the electrical conductor inside may be exposed to touch or it can also unintentionally come into contact with things that can carry electric current.

This scenario would present a high risk of electric shocks.

Therefore, we protect the electric cables so that they do not present the dangers of electric shocks to people (or animals).

A second reason to protect the cables is to make sure the electrical system stays reliable.

When the cable PVC covering is damaged, the conducting metal can come into contact with other metals that are in contact with earth.

Visit this post, Electric conduit installation pictures, to see a few more conduit pictures.

Picture 10 – HV substation’s main earth bar



What you see in the above picture is the HV substation’s main earth bar. The purpose of having the main bar is simple.

All earthing conductors inside the HV room would be connected to this bar. That is the reason you can see in Picture 2 a number of ready-made termination holes complete with bolts, nuts and spring washers.

Notice the main copper earthing tape mounted along the substation wall in Picture 1. This is the main equipotential earthing conductor for this electrical room.

It should run through all perimeter walls of the room at a height of approximately 12 inch from the substation’s finish floor level. That is why you can see that in Picture 2 the left-most and right-most terminals have been connected with a horizontal copper tape conductor.

An ideal installation would have the main equipotential conductor run in a ring around the perimeter walls and both conductor ends connects to the main earth bar at the left-most and right-most terminals.

There are more pictures of the main earth bar at this post, Substation main earth bar pictures.

Picture 11 – Dangerous electric panel installation



Why would I want to show you these pictures?

There was something wrong with this electric panel installation. The telephone DP on the right is not a problem, but the installation of the electrical panels was absolutely not acceptable.

This project was a high-rise office building.

At every floor there were a number of electrical panels to serve all the lighting and power loads on that floor including the lighting, switched socket outlets, toilet exhaust fans etc, etc.

A few of the panels were located inside the riser room of each floor.

However, since each was a large area some panels needed to be located at the office area. Wiring directly from the electrical riser would be unnecessarily too long and a waste of wiring cost.

Therefore, the electrical consultant proposed that these electrical panels be located along the corridors throughout the building. The design architect was requested to provide small rooms to house the panels.

Alternatively, small electrical cabinets with lockable doors and sufficient work access and ventilation would be acceptable.

Read the full article at this post, Electric panel installation pictures. There are some more pictures there too.

Picture 12 – Electric trunking running below soffit of a concrete floor slab



No electrical installation work of a significant size can be done properly without the use of an electric trunking.

A trunking is a larger size of a conduit. When you need to run a number of electric conduits along each other for a significant distance, then consider using a trunking in place of the conduits. There are so many sizes you can choose from.

The above picture is an example of a trunking installation above ceiling level, under the soffit of the concrete floor slab.

I also labeled some of the other services there for the benefit of those non-electrical readers who need pictures like this for reference, to know what is what among the myriads of pipes, conduits and trunking running above the ceiling level.

Visit Electric trunking installation pictures to see more pictures on electrical trunking and how they are installed.

Picture 13 – Cast in situ light pole mounting base



Some readers may say that this is a strange way to locate a light pole, which is above the drain. A more normal method would be more or less like the one in Picture 13 below.

Picture 14 – Precast concrete base for compound light poles



Here the design-and-build contractor had a problem of locating a few of the compound light poles at an open carpark area because there were several drains running between carpark boxes.

These drains were supposed to be located at the boundary of the land being developed.

However, it turned out that with the presence of the drains the actual land space for the landscaping works (e.g. trees, shrubs, etc) was too narrow to grow larger trees.

Therefore, the client agreed that the drains be relocated through the middle of the carpark area.

Construction people tend think that electrical things are very flexible and easy to be moved and kicked around just like a wiring cable.

I never liked that notion. It is true in this case, however.

The main contractor asked me how to place the pole bases on top of the drain cover.

I told them that the only real solution I have ever seen in such situations was only by constructing a cast in concrete base together with the drain, with the construction drawings of the light pole’s concrete foundation designed and endorsed by the civil work’s design consultant.

The result was what you see in Picture 12 above. More of these pictures can be seen at this post, Compound Lighting Installation Pictures.

Picture 15 – MATV antenna brackets mounted to a roof wall



When I started this blog, I wanted to make it specialized in only electric supply systems for building constructions and its related construction works.

However, I have also always asked myself what to do with all the pictures on ELV (extra low voltage) systems and telephone works that I took during my works.

In fact I have quite a number of pictures on the installation of other building services such as the public address system, the firemen intercom, audio visual and conference system, etc.

It has been such a waste. Those pictures can be of use to many people such as those whose need real installation pictures of the systems in real construction works.

Even I myself was having such needs during my early days in the electrical world. Of course, now anyone can search among the tens of thousands of the manufactures’ and suppliers’ websites specialized in these systems.

However, often we only find nice pictures and often we do not want nice pictures.

We want the real construction pictures, pictures that are not biased towards any particular supplier or manufacturer.

For this reason, I am expanding the scope of this blog to also include the installation pictures of building’s extra low voltage (ELV) services and telecommunication systems.

Today interested readers can see a few pictures on the installation of MATV antenna brackets. An MATV single line schematic diagram is also shown. Visit this post, MATV Antenna bracket pictures.

Picture 16 – How to install a motorized overhead projector



I took this picture a few months back.

The electrical contractor produced a mock-up unit of the installation bracket for motorized overhead projector.

I just sent it here plus a few more for anybody who has no idea at all how it is done.

The overhead projector was for meeting rooms. There were about thirty units to be installed through the building.

This one was done so I could check and comment.

You can see all the pictures at this post, How to install overhead projector.

Picture 17 - Compound lighting feeder pillar



A building construction of significant size is usually not complete without at least one small outdoor weatherproof feeder pillar.

I have uploaded a few pictures of feeder pillar including existing and new ones at this post, Feeder pillar single line diagram.

There are also a few diagrams there including the cubicle dimensions of a feeder pillar and a simple single line diagram.

Picture 18 – Fire-rated (FR) cables installed on vertical cable tray



The above picture shows the installation of FR electrical cables.

There is nothing special about the installation of the fire-rated (FR) cables. Even though these cables are a direct replacement of mineral insulated copper cables (MICC) for high-rise buildings, the installation here is the same as for normal XLPE or PVC-insulated cables.

In Picture xx, two vertical submain circuits employ FR cables installed on a vertical cable tray. These cables were taken in a cable riser room at a multi-storey building.

All these cables are single-cores. The circuit on the right (with the smaller cables) was supplying the lift motor room at the roof level of the building.

The copper tape on the right edge of the vertical cable tray is the common earth and it is connected to the main electric grounding bar at the LV Room on the ground floor of the building.

The LV Room houses all main switchboards (MSB’s) for the building’s low voltage electrical distribution.

The circuit on the left edge of the cable tray was supplying two fan rooms, which were also at the roof level.

The loads of the fan rooms were mostly electric driven motors that run fire protection fans. These include smoke spill fans, staircase pressurization fans, etc.

These fan loads are significantly large. That is why the cables are of bigger size than those for the lift motor room electrical panel.

You can see more of the pictures at this post, FR electric cable installation pictures.

Picture 19 – 1000 KVA standby diesel generator



No building of a significant size can be operated without at least a small standby generator installed.

The primary reason for having the standby generator is for fulfilling the requirements of the fire department to have the supply readily available for operating the fire protection and fire fighting equipment.

The building itself would normally have some equipment and lighting that need to be operable even when the public electricity supply fails.

This would require the use of a back-up generator or a supply battery system.

See more installation pictures of the standby diesel generator at this post, Standby electric generator pictures.

This is the first part. I still have more pictures of this installation which will be uploaded soon. Keep checking this post for updates.

Picture 20 – Bollard light



Well, I thought this bollard light looked nice at the children playground near at rest area and food stalls on my way from my workout routine at a local gym.

I do not have much to say about the bollard lighting. They are just pictures of existing lights that I thought may be useful to someone.

However, for readers who have to deal with the installation of this type of landscape lighting, I did attach in this post a section diagram that shows a little bit more details. I hope it helps.

Landscape lighting falls within the jurisdiction of landscape architects. So I do not normally spend much time with them.

When I have to prepare an external lighting layout that also include the landscape lighting during a concept design stage, I usually just copied the layout of landscape lighting from previous projects, prepare the electrical distribution system for the lights and count the number of light fixtures.

The purpose was to capture a rough approximate of the cost for the landscape lighting works. We must get the money first. Once the money is available, there are so many ways to get the job done.

See more of the bollard light pictures at this post, Bollard light pictures.

Picture 21 – Electric closet



The electric closet in the above picture has been done for a multi storey office building.

I wrote an article earlier on the protection of electrical panel at a multi storey office building. You can read the article here, Electric panel installation pictures.

In that article I gave a storey of how reluctant the main contractor was to provide an electrical room or cabinet in order to restrict access to the electrical panels and protect them from damages.

Access to the panel by unqualified people may lead to abuse, improper operation of the instruments inside the panels, or accidents by touching the LIVE parts inside the panels.

These panels were three-phase panels with 415V of voltage between the phases. Accidentally touching the live parts at this voltage would lead to very serious injuries. Electrocutions and immediate deaths are common results of electric shocks at this voltage.

Read the rest of the article here, Multi storey building electric closets.

Picture 22 – Substation CO2 fire protection cylinders being installed



All electrical substations and main switchrooms need to be provided with a fire protection system.

If the substation building is a separate building, some local offices of the electricity supply authority and the local office of the Fire Department may consider portable fire extinguishers as adequate.

However, electrical rooms that are part of an occupied building are usually required to have some form of automatic fire extinguishing system such as a CO2 system.

The above picture shows a CO2 automatic fire extinguishing system installed inside a standby generator room.

Picture 23 below show an automated fire curtain right above the inside opening of the genset room’s air intake silencer.

The curtain sheet is in the rolled-up state. When the automatic CO2 system is activated and the gas discharged, this curtain (and all other fire curtains installed in the room) is automatically released and rolled down to block the air passage.

This action allows the CO2 gas to totally flood the room and extinguish the fire inside.

Picture 23 – Automatic fire curtain over fresh air inlet silencer



What fire protection to be used for an electrical substation depends on the preference of design consultants and the minimum requirements of the local Fire Authorities.

However, in some projects, a substation building or substation room (e.g. HV switchgear room) needs to be constructed and equipped (excluding the electrical distribution system equipment), and then handed over to the local electric supply authority as one of the agreed conditions to obtain the supply.

In these types of arrangement, the minimum requirements and preferences of the local office of the electric supply authority must also be met.

The fire authorities usually have an established requirement of what system is required in a substation room. The design engineers usually prepare their design based on these requirements and the supply authority’s requirements.

See the rest of the pictures here, Substation fire protection system.

Pictures of electric shock injuries

I have uploaded a few pictures of electric shock injuries, but I know many readers are easily turned off by the sight of these serious injuries. So I do not put them in this post.

You can check out this post to see them, Electric shock injury pictures.

Diagram 24 – Electrical riser room



During the design of an electrical installation for a building, spaces that are required as electrical rooms need to be provided for very early in the planning and design process.

I will try to present this in a form of a few basic concepts so that non-electrical readers can benefit from it.

There are also a few diagrams at the end of this post, but I do want to go too technical here as this may turn off the non-electrical readers.

If you need a more technical discussion, I will send a few posts of electrical substation layout and design in future.

Read this article here, Building's electrical rooms layout.

Picture 25 – Dangerous feeder pillars



I think anybody with even a minimal amount of knowledge on the hazards presented by electrical equipment installed in public places know what is wrong with the feeder pillars in the picture above.

I am not talking about age of the feeder pillars.

I know that everything gets old some day. Machines get worn out, the materials get deteriorated and the lovely paintwork fades out.

They do get old, just like us.

However, machines and equipment that can endanger people especially children should be designed and installed with safety as the most important criteria.

The feeder pillars above have failed in that respect.

Read this article here, Feeder pillar hazard pictures.

Picture 26 – The inside view of the electrical socket extension unit



Have you ever wondered how it looks inside the extension unit of an electrical power socket? The pictures in this post can help you appreciate what is going on inside this piece of common household items.

I think most readers can understand the picture clearly with the labels that I added.

However, for the benefits of absolute beginners that need explanations on what does what in this picture, let me just give brief descriptions.

Visit the post here, Electrical socket extension unit.

Diagram 27 – Simple house electrical layout



Anybody looking for a layout and schematic diagram of a simple electrical installation?

The above electrical layout is very old.

At least 30 years old or more.

You can see that by the number of electric socket outlet in the bedrooms and the kitchen.

A modern bedroom would need at least a few sockets in each room. You would need one for the table clock, table lamp, a television maybe, etc etc.

One electrical socket as shown in the electrical layout would definitely be not enough.

However, I believe there are still great many areas in this world that still lacks even the basic supply of household electricity.

So this simple house electrical design is still useful to great many people.

In fact, this design is more relevant. It is also more easily understood by beginners of electrical installations.

Read this post, A simple electrical installation, for a full article and the single line diagram for the above layout.

Picture 28 – Underfloor trunking installation work in progress



The underfloor trunking system has been around for a long time. The first time I saw it was inside an application guide published by a public telecommunication company.

The technical manual was already very old and I was in the first year of real professional work after my graduation. That was 23 years ago.

Why do we need an underfloor trunking system?

An underfloor trunking system is an alternative way of providing the dedicated routes to run electrical cables, telephone cables or any other wiring cables you can think of.

I said “wiring cables”. An 11KV cable is not a wiring cable. A 25 sq.mm electrical feeder cable to supply an 11 KW fire pump panel is not a wiring cable.

(Note: 25 sq.mm means 25 millimeter square. It is a measure of the net cross-sectional area of the electrical conductors of an electric cable).

The 1.5 sq.mm cables that are used for wiring the office lights are categorized wiring cables.

See the underfloor trunking pictures here: Underfloor trunking pictures.


Picture 29 – Sharp edges of a site-fabricated 45-degree electrical trunking bend



What will be the problem if an electrical contractor fabricates some of the accessories of an electrical trunking system by hand at the construction site? Why do I make an issue of this matter?

Majority of Clients and Consultants that I know specifically state that all electrical trunking and the related accessories should be factory-manufactured and should preferably be obtained from the same manufacturer.

This means that all parts and pieces that make up an electrical trunking installation should be purchased as finished products from factory.

What if the electrical subcontractor does not follow this requirement?

Factory-manufactured accessories have much better quality; there is no doubt about that.

However, is there any other significant reason for this specific requirement other than the difference in qualities of the products?


Read the full article at this post, Site-fabricated electrical trunking. There are a few more pictures there too.

Image 30 – Dimensions of a concrete foundation for a 5m compound light pole



A friend asked for the size of this thing. So I uploaded a few images.

Read the full article at this post, Compound lighting foundation size. There are a few more images there too.

Picture 31 – The electrical manhole being unloaded



The picture above shows an electrical manhole intended for underground installation being unloaded from the transport truck.

Most building works require at least one or two underground electrical manholes. That is because a building of significant size usually require a few hundred amperes of electric current at low voltage (i.e. 240 volt, 3 phase current).

Above a few hundred KVA (kilo-volt-amperes), the electricity supply authority usually delivers the electrical power to the consumer loads at higher than 240 volt, usually at 11,000 volts.

(Note: 100 amperes x 240 volt x 3 phases = 24,000 VA x 3 phases = 72,000 VA = 72 KVA. For readers who are intimidated by the KVA term, this is what KVA is. That is measure of electrical power delivered to a building. It is also the most common unit used in specifying the size and rating of electrical equipment and switchgears.)

Okay, back to the electrical manhole.

When the supply is at 11,000 volts (i.e. 11 KV), high voltage cables installed below ground level (i.e. underground) is the most popular method of electricity distribution unless the building is in remote areas such as the countryside.

So, in building works, we need at least one or two of these manholes to bring in the authority cables from outside the boundary of the building works to the electrical substation inside the building compound or the inside the building itself.

Read the full article at this post, Underground electrical manhole.


Picture 32 – Improvised installation of electrical trunking, air-conditioning ducts, fire protection pipe work and a floor beam



The few pictures that I show in this post are a demonstration of what can happen when a proper coordination is not carried out between the mechanical and electrical services installation in a multi-storey building.

Somewhere among my previous posts, you can find examples of good coordination between the mechanical and electrical services installation.

However, here I wish to show you the opposite side of it. The above is not the worst case examples. I have plenty of pictures showing much worse scenarios which I will show you in future posts.

A reminder for the beginners in electrical installation works: Learn from the mistakes that other people have done and plan your work accordingly.

This is a very expensive lesson if you have to learn it from personal experience because rectifications, relocation or corrections in large installations can be very expensive and time consuming.

Read the full article at this post, M & E Coordination.


Picture 33 – Example color codes for a few electrical services



This post gives some examples on the identification of the different electrical services inside a building.

The three conduits with the color code bands in the above pictures are part of what we call in building works as electrical services.

However, electrical services are not the only ones that require some means of identifying what they are for.

Mechanical services also really need their piping, trunking, etc to be provided with some identification.

In some installations such as hospitals, there are so many services under the mechanical category. At certain locations in a hospital complex, it is almost impossible to know which pipe is for what. (Remember that an electrical G.I. (galvanized iron) conduit is just a metal pipe.)

During maintenance, long after we the construction people have completed and commission the building with all the mechanical and electrical services fully tested and operational, the maintenance people could be cursing us every week for not providing sufficient identification for each of the services inside the building.

During operation and maintenance of the building, insufficient identification on each of the services throughout the building can lead to serious accidents.

Why do I talk about mechanical services? Because they often run along the electrical services. Now and then the parts and materials between the two disciplines look and feel just the same.

Read the full article at this post, Electrical Services color codes.

Picture 34 - 1600 kVA transformer delivery pictures



I just uploaded some pictures of 1600KVA transformers being unloaded from the delivery truck at a project site.

You can see all the pictures here, 1600 kVA Transformer Pictures


Picture 35 – 10 meter light poles: the lower piece


I took a few pictures of the storage area for compound lighting parts at a project site recently. With these pictures I think I have explained the whole system of compound lighting in this blog. So this post wraps up the topic of compound lighting. Of course, if I find more pictures that I think readers would be interested in, I will attach a link to this post also.

See all the pictures at the storage yard here, Compound lighting storage yard.

Picture 36 – The mould for exothermic welding for jointing 25mm x 3mm grounding copper tape and a copper-jacketed steel ground rod.


I believe I have uploaded to this blog quite a number of pictures on electrical grounding. However, there is one work of the grounding system that I have always wanted to show the readers especially true beginners (i.e. students and young engineers). That is the process of exothermic welding.

The above picture is one of the few that I just uploaded. You can see the rest of them here, Electrical grounding .

Picture 37 – Cable ladders at Consumer’s High Voltage Switchgears


Cable ladder is one of the most important components of a building’s cable support system. The above picture show an example of a new installation. You can see the rest of the pictures at this post, Cable ladder pictures.

Picture 38 – Electrical and mechanical services above the ceiling of an office building




 Some few weeks ago a reader left a message on one of my blogs asking how to connect a branch conduit to a steel trunking. So I uploaded to this post a few pictures showing the connections between electrical conduits and trunking. Those pictures should be self-explanatory enough how to make the connection. See all the pictures here, Conduit to trunking connections.

Diagram 39 – Overall layout of the substation electrical rooms for a new office building


Below is the layout of the electrical rooms for a post that I sent earlier, Cable ladder pictures.


The earlier post was about cable ladders. I know it can be difficult for some beginners to imagine the overall arrangement of the electrical rooms (and therefore the cable ladders) at the substation without the aid of some layout diagram.

The above diagram should be able to give some help.

You can read the rest of the post here, Substation rooms layout diagram.

Picture 40 - Exothermic welding process set-up labeled


The above picture shows the set up for a cable to cable connection.

I will not write much today and I have serious doubt that I will be able to write long posts again in the near future.

The best I can do is to show you some pictures. When I have more time I will write longer.

Note that the part that I labeled “explosive powder” is not really explosive powder. Well, IT IS explosive, but it is not an EXPLOSIVE.

It is actually some powdered mixture of copper oxide and aluminium.

When ignited, the mixture produces a very high temperature reaction that molten the copper and aluminium components which then flow into whatever cavities between the conductors to be joined, as well as form a thick layer of alloy envelope around them.

See the rest of the photos here: Exothermic welding: Cable to cable connections

Picture 41: Underfloor trunking below structural rebars



I have published quite a number of pictures on underfloor trunking systems.

These underfloor trunking systems, together with their floor draw boxes (i.e. junction boxes) and floor service boxes, have so far been installed inside the concrete screeding of the concrete floor.

In this installation method, the reinforced concrete floor slab is constructed first.

However, the construction of the concrete floor is not yet completed with the completion of the reinforced concrete.

A layer of concrete 50mm to 75mm thick is to be poured and leveled on the finished reinforced concrete to make a finished concrete floor. This layer is called 'concrete screeding'.

It is within this top concrete layer that an underfloor trunking system is installed, or "embedded" as some people call it.

However, in the new picture that I showed above, the underfloor trunking is not installed in the screeding layer (In fact there is no screeding layer here).

The finished floor level here has been designed to be just 50mm above the top of the top of topmost reinforcement steel bars (called "rebar").

Read the rest of the article here: Underfloor trunking below structural rebars

Picture 42 - Electric cable bridge
(Click on the picture to enlarge it)

Continuing the tradition of sharing engineering knowledge through pictures, today I am sharing with you some pictures of cable bridges for electrical cables.

Visit Electric cable bridge to see more photos of cable bridges for electrical cables.

Picture 43 - Electric cable drums


It is very important that great care is exercised at all times when handling cables.

Every precaution should be taken to avoid dropping a drum of cable. Dropping off cable drums, even from a short height, will flatten the layers of the cable nearest to the barrel of the drum.

Depending on the length of the cable, the type of the cable involved and the height of the drop, the weight from the outer layers can cause damages to the inner layers that are very difficult to ascertain.

Similar distortion to the cable will also occur if the drum falls on its sides.

I have a true story to tell on mis-handling of cable drums. It was from one of my earlier projects. Read it here, Electric Cable Drum Pictures.

Picture 44 - A weather-proof 13A IP66 power socket

This picture is from one of my old projects.

The location is on the roof top of an attached 5-storey podium block. This level is used as a secondary plant room where air-condition cooling tower and fire fighting water tanks are located.

A fire fighting main pump room is also nearby here.

Therefore, this outdoor area is a good location as a maintenance work area that may be required once the office complex is operational.

The conduit that you see along the parapet wall runs all around the roof top. IP66-rated outdoor power sockets and bulk-head lighting fixtures are installed at uniform intervals along the conduit run.

See the post and more weather-proof socket outlets here, Weatherproof 13A switched outlets

Copyright http://electricalinstallationwiringpicture.blogspot.com Electrical installation pictures